Progress: We had a meeting on Monday with a representative from the cabinet company that our architect recommended. We really liked what we heard and saw and we are now waiting to get a final quote on the cabinets in the kitchen (including pantry and china closet), master bath and living room.

can Collage

Meanwhile, the crew spent the week making progress in the house. The beam work is done in the kitchen and they’ve started work on our stair remodel.

beam done

The guys also framed our new shower and linen closet in the master suite.

master

Insulation work is also happening in the living spaces downstairs.

insul

Finally, another layer of paint has been done on all wall surfaces upstairs. We expect ceilings to be tackled next week.

land Collage

Details: We finally picked out a back splash in the kitchen (surprise – it’s not white!), lights for the upstairs landing, toilets, and a chandelier for our dining room.

lightCollage

As I previously mentioned, we listed our beloved Cliffwood just after midnight on Friday, October 2nd. Within 24 hours, we had 6 showing set up and we ended up having 8 before the weekend was over. We’ve had another 6 showings since then and we had an open house on Sunday.  We have our first offer in. Please cross your fingers for us!

Purchases: None

Challenges: There are so many choices…for everything. And I’m really starting to second guess some of my choices. What a vicious cycle.

Wins: …However, we are still very much enjoying this process!

plans

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s